Workplan

Starting: 1/10/2005

Duration: 36 months

Stage of the project

Results : at the end of this stage, we have realized / produced

1 Stage 1

Launching of the project
( duration : 1month)

Document of Validation of the work plan, of responsibilities,

decisions about administrative, legal, financial matters.

2 Stage 2

Specifications
(
duration : 8 months)

a) Specification of needs of target groups
b) Specifications of the device Nodes
c) Methodology of training based on Nodes device
d) Methodology of validation of the device
e) Formalisation of interfaces "Tools – Services – Content",
f) Definition of the contents of the training module for validation
g) Strategy of communication and communication actions

3 Stage 3

Yearly meeting of the partnership
(duration: 1 month)
Face to face duration : 3 days

Intermediary report N°1, validation of the works of phase 1

Adjustment / preparation phase 2

Presentation of the experts’ report

4 Stage 4

Developments
(duration : 12 months)

a) Formalization of the tools
b) Development of the tools
c) Production of the contents
d) Technical running modes of the device
e) Methodology of training based on / integrating the device Nodes
f) Harvesting "individual knowledge"

5 Stage 5

Yearly meeting of the partnership (duration work : 1 month)
Face to face duration : 3 days.

Intermediary report N°2, validation of the works of phase 2

Adjustment / preparation phase 3

Presentation experts’ report

6 Stage 6

Deployment ( duration : 9 months)

The phases 3 and 4 will be detailed at the end of phases 1and 2

7 Stage7

Yearly meeting of the partnership (duration : 1 month)
Face to face duration : 3 days.

Intermediary report N°3, validation of the works of phase 3

Adjustment / preparation phase 4

Presentation experts’ report

8 Stage 8

Validation ( duration :5 months)

The phases 3 and 4 will be detailed at the end of phases 1and 2

9 Phase 5

Exploitation (duration :1 month)

Intermediary report N°4, validation of works of phase 4

Presentation experts’ report, start of exploitation. Final report

 